                          WP Contracts:
                        
                       
                        
                          List of Contracts
                          
                        
                          
                            LIST OF CONTRACTS AND MEMORANDA PREPARED FORENGINEERS COMMISSIONE . B. & A. L. STONE COMPANY     Agreement dated Nov. 15th, 1905 covering contracts "A", "B","C","D" and "E" from a point near 25th ave. East Oakland to Myers St.Oroville, Cal.     Contracts "A", "B", "C", "D" and "E". Also SupplementalContract regarding loaning money to contractors accompanied eachof above contracts .THE UTAH CONSTRUCTION COMPANY     Agreement dated October 31st, 1905 covering territory from Cityof Oroville to California-Nevada State Line .     Contracts "A", "B", "C", "D", "E", "F", "G', "H", "I ", "J " and"K" and Death to Desert and Silver Zone Pass to Salt Lake City.Also Supplemental Contracts regarding loaning money to contractorsaccompanied contracts "A", "B", "C", "D", "E" and "F"MEMORANDA AS FOLLOWS :     Showing contracts for all steel bridge material - The AmericanBridge Co. of N.Y. dated Aug. 17th, l 906 - King Bridge Co. dated Aug. 7th,1907, McClintic-Marshall Const'n. Co. dated July 20th, 1907 -Baltimore Bridge Co. dated Aug. 13th, 1 907 – McClintic-Marshall Const'n.Co. dated Sep. 13th, 1 907     Contracts with Geo. F. H. Hicks dated Feb. 5th, 1906 and J .H. Robertsdated Jan. 7th, 1907 covering rental of tracklaying machines. Sheet No. 2 LIST OF CONTRACTS AND MEMORANDA PREPARED FOR ENGINEERS COMMISSION      Contracts with Colorado Fuel & Iron Co. covering delivery of85 Lb. steel rail - dated Dec. 20th, 1904, Aug. 3rd, 905, Nov 1st,1905, Jul y 26th, 1906 and Oct. 20th , 1906 S.F. 8/12/08. Transcribed – Paul Finnegan 5/15/2021
                          
                            Memorandum of Contracts
                          
                         
                        | WESTERN PACIFIC RAILWAY COMPANY. |  |  |  | MEMORANDUM OF CONTRACTS WITH |  | COLORADO FUEL & I RON COMPANY |  | for |  | STEEL • RAIL |  | ALL 85 LBS. PER YARD |  |  |  | Date | Delivery point | Gross Tons | Price 1st qual. | Price 2nd qual. |  | 1904 |  | Dec. 20 | Stockton, Cal. | 500 | $20.00 GT | $27.55 GT |  |  |  | 1905 |  | Aug. 23 | Salt Lake City | 20,000 | do | do |  | Nov. 1 | Stockton, Cal. | 5,000 | do | do |  | 1906 |  | Jul.26 | *Various | 50,000 | do | do |  | Oct.20 | Beckwourth | 550 | do | do |  | Shop Inspection |  | * To be shipped to points as designated by V.P. & C. R. of W.P.Ry.Co |  | from time to time. |  | ALL F. O. B. WORKS OF C. F. & I CO . |  | S .F. 8/10/08 |  |  |  | Transcribed by Paul Finnegan 5/15/2021 |  
        WESTERN PACIFIC RAILWAY COMPANYMEMORANDUM OF CONTRACTS FOR PURCHASE OF
 STEEL BRIDGE MATERIAL
 
 
 
        Contract:The American Bridge Co. of N.Y. Dated August 17th, 1906.
 All steel work for following bridge s fob cars East St. Louis
 ill. PRICE $3.13 cwt .
 Bridges 7, 7 1/2, 8, 9, 10, 10 1/4, 10 1/3, 10 2/ 3, 11, 12,
 14, 15, 16, 16 1/2, 17,** 18, "A", "B", "C" and "D".
 TOTAL WEIGHT 9,868,643 Lbs.
 
 Contract:
 King Bridge Company, Dated August 7th, 1907
 All steel work for Transfer bridge Oakland Mole fob, works ,
 Cleveland . PRICE $3.45 cwt.. .
 TOTAL WEIGHT 295,871 lbs.
 
 Contract:
 McClintic-Marshall Const’n. Co. Dated July 26th, 190 7
 All steel work for following bridge s fob bridge Company's works
 PRICE $2.80 cwt .
 Bridges: 16*, 17***, 18 1/2, 19, 20, “E”, “F” and “G”
 TOTAL WEIGHT 2,949,631 lbs.
 
 Contract:
 Baltimore Bridge Company, Dated August 13th, 1907.
 Steel work for Bride No. 19 ½ over slide ravine about 1 mile
 West of First Crossing North Fork.  fox Company’s works Baltimore
 PRICE $2.95 cwt.
 TOTAL WEIGHT 281,622 lbs.
 
 Contract:
 McClintic-Marshall Const’n. Co. Dated Sept. 13th, 1907
 Steel Bridge No 18 1/4. fob Pittsburg, PA PRICE $2.80 cwt.
 TOTAL WEIGHT 61,868 lbs.
 
 *Contract with McClintic-Marshall Const’n Co. Br. 16 covers one
 additional 80’ span for this bridge
 **North Channel Yuba River
 ***South Channel Yuba River
 
 S.F. 8/11/08.
 
 Transcribed by Paul Finnegan 5/15/2021
 
 
        WESTERN PACIFIC RAILWAY COMPANY
         
        MEMORANDUM OF CONTRACTS FOR RENTAL OFTRACK LAYING MACHINES
 
        Contract:Geo.  F. H. Hicks - Dated February 5th, 1906
 Use of one or more Improved Harris Tracklaying Machines
 Rental $20.00 per mile of track laid, less 12 1/2 %
 
 Contract:
 J. H. Roberts - January 7th, 1 907
 Use of one Roberts Tracklaying Machine
 Rental $20.00 per mile
 
 
 S.F. 8/11/08
 
 Transcribed by Paul Finnegan 5/15/2021
 
 
                        
                          WP Contracts: Utah Construction 1905
                        
                       
 
                        
                          E.B. and A.L. Stone Co. -  1905
                        
                       |  | 
        
          | 
              
                Desktop Home | 
                Mobile Home | 
                Shop Online |
                Contact |
                Subscribe |
                Privacy
                
 
  |  |   
              
                Operated by the Feather River Rail Society, a California 501(c)3 Non Profit Organization
              
             
              
                700 Western Pacific Way, P.O. Box 608, Portola CA 96122-8636 | 1-530-832-4131 | email us at:  
                info@wplives.org
              
             
              
                Copyright © 2025 Feather River Rail Society.  All Rights Reserved.  Page last updated:  Wednesday October  8, 2025 07:35 PDT
              
             |